To the central content area

Taitung County promotes environmental permit integration plan in 2012

Absrtact
The implementation period of this plan is from February 1, 2020 to December 31, 2020, but the work projects need to be completed before November 30, 2020 (excluding the revised version of the final report and the final version of the final report). The statistics of work projects and execution results are as of November 30, 2020. The summary is as follows: (1) Stable operation of automatic monitoring (monitoring) of water quality and quantity and connected transmission facilities system: This project confirms the connection status of the connected objects every day (the agency is working) and maintains the operation of the host equipment of the management connection transmission facility system. Measures have been taken for the "Jilin Factory of Buddhist Education Enterprise Co., Ltd.", "Taitung Factory of China Pulp Co., Ltd.", "Taitung Water Recycling Center" and "Zhiben Water Recycling Center" that should set up CWMS in this county. Review the instructions and measures confirmation report and check the on-site connection signal, and send a letter of the check results and improvement tracking status to the agency for reference (2) Water pollution source pollution prevention and control operations: This project has accepted and completed the review of 107 applications, totaling 207 applications. There are still 1 application under review and 5 supplements for various types of license documents. There are still 2 automatic continuous monitoring reports under review, totaling A total of 3 cases are under review and 5 cases are pending. We will continue to track the progress of the cases and complete the review, and 26 current inspections have been completed during the review of license applications. In addition, the review of periodic testing declaration data for the second half of 2011 and the fourth quarter of 2011 has been completed, and the results have been submitted to the Environmental Protection Bureau for review. Data on various water licenses (documents) within the jurisdiction that are valid for less than 6 months and have not yet been applied for extension are compiled every month. The statistics are as of November 2020. Currently, there are 5 companies that should be extended but have not yet applied. (3) Improving the quality of implementation of water pollution prevention and control regulations: As of November 30, 214 inspections have been completed, with a completion rate of 100%. According to the distribution of inspection industries, animal husbandry is the largest, followed by catering industry, tourist hotels (restaurants), and then hospitals and medical services. Institutions, these three industries accounted for 65% of the total number of audits; 50 water quality sampling and testing operations have been completed. Currently, the issuance of water quality testing reports has been completed, and the testing data of 3 companies did not meet the water discharge standards. Completed 8 in-depth inspections, including the Catholic Diocese of Hualien Medical Foundation Taitung Our Lady’s Hospital, Taipei Veterans Hospital Taitung Branch-Attached Psychiatric Ward, Fuye Hotel Co., Ltd. Taitung Branch, Sailfish Golden Business Hotel Hotel Co., Ltd., Zhiben Water Recycling Center, Zhenhe Ranch, Guanshan Tzu Chi Hospital, Luye Ding Development Co., Ltd., etc. The tracking of unimproved projects in the 111th annual execution function evaluation has been completed. Mingyuan Development Co., Ltd. has planned to apply for public sewage sewer management. All wastewater generated by the business will be included in the public sewage sewer system; and all deficiencies in Hewang Ranch have been improved. . Based on the screening principle, two enterprises, "Taitung County Waste Incineration Plant" and "China Pulp Co., Ltd. Taitung Plant" were selected to conduct this year's functional evaluation operation. The on-site evaluation (preliminary evaluation) was completed on July 10, 2012. and sampling operations, on August 17, 2012, together with experts and scholars, we conducted on-site re-evaluation operations, and finally held a negotiation meeting for the evaluated units on August 25, 2012. (4) Analysis and improvement measures on pollution reduction at key water quality measuring stations The annual specific actions and key performance indicators (KPIs) of key measuring stations in the 112-year "Water Pollution Prevention and Control Assessment" have been revised based on the Environmental Protection Agency's review opinions. The 112-year "Water Pollution Prevention and Control Assessment" results report, annual results summary, self-evaluation form and presentation will be completed and submitted to the agency for reference by September and the end of October. (5) Water pollution prevention and control fee collection review and application effectiveness evaluation: The collection of water and sewage fee collection data shows that there are 113 households that should declare for the 11201 period in 2012, and all of them have completed the declaration. The declaration rate for this period is 100%, and the total payment amount is 3,012,398 yuan. Assisted the agency to handle the suspension and settlement of water pollution prevention and control fee declaration cases for one operator - Binlang Ranch. In addition to completing the on-site inspection of enterprises with doubtful water and sewage fee declarations notified by the Environmental Protection Agency in 111, 6 additional institutions were added The inspection work was carried out and a total of 20 on-site inspections were completed. The inspection results were summarized and sent to the agency for reference. (6) Operation and management of water environment patrol team This plan has completed 3 sessions of cleaning streams and rivers, 2 sessions of energy-enhancing training activities and 1 out-of-county visit and observation activity; completed 1 training session for water environment guides. Assisted in handling the 112-year patrol team management guidance meeting on March 31, 2012, and put forward relevant proposals for the volunteer operation of the patrol team, which were discussed and handled by the chairman and on-site captains. It has completed assisting the water environment patrol team in reporting 33 cases and clearing them up. It has assisted the county in the implementation of surface water body garbage interception operations, and the implementation results will be reported online in the "Ground Water Body Garbage Interception Management System" before the 10th of the following month. The current score has reached a total of 93 points. (7) Domestic sewage pollution reduction operations: This year, a stall will be set up to promote the reduction of domestic sewage on June 18, 2020, in conjunction with World Oceans Day. (8) Promote environmental licensing integration plan This project has assisted the Buddhist Tzu Chi Medical Foundation Guanshan Tzu Chi Hospital, Haoye Quarry, Taipei Jung⺠ General Hospital Taitung Branch, Taipei Jung⺠ General Hospital Taitung Branch - Attached Psychiatric Ward, Hao Jian Co., Ltd. Dongxin Factory, Dongji Medical Foundation Taitung Christian Hospital, Taiwan Christian Elders Medical Foundation Taitung Kaikai Memorial Hospital, Yangchen Enterprise Co., Ltd., Shangyong Development Co., Ltd. and Green Stone Environmental Protection Resources Co., Ltd. Wait for 10 voluntary operators to complete the drawing of air, water, waste, and toxic (concern) chemical pollution flow maps. In addition, we targeted the Catholic Diocese of Hualien Medical Foundation Taitung Notre Dame Hospital, Zhiben Water Recycling Center, Ruisheng Sand and Gravel Co., Ltd., Triumph Starlight Hotel Co., Ltd.-Triumph Starlight Hotel, RT-Mart Distribution Co., Ltd. Taitung Branch, Eight companies, including Xinyiqun Industrial Co., Ltd., Yiyuan Sand and Gravel Co., Ltd., and Luyuan Sand and Gravel Yard, are revising and confirming pollution flow maps. (9) Promotion plan for ammonia nitrogen recovery from livestock wastewater: This plan has completed 2 large-scale farm and small farm or centralized processing site policy publicity briefings, 1 agricultural and animal husbandry matching briefing, 1 strengthening of biogas slurry and biogas residue farmland fertilizer use plan extension to promote the scope of animal husbandry principles 13 households were sampled for wastewater, and 22 households in the livestock industry were provided with follow-up follow-up guidance for applying for water release and reuse. In addition, we completed inspections on the irrigation status of 26 secondary biogas slurry and biogas residues, and assisted them in completing regular monitoring sampling analysis and reporting operations. (10) Other cooperation matters: Cooperated with the agency's instructions to attend 21 relevant meetings or training sessions; assisted the agency in conducting regular sampling operations at water quality measuring stations.
Keyword
Water pollution, water and sewage fees, river assessment, water environment patrol team, resource utilization of livestock manure
Open
top